Gore Street's 12 November page prints €147m committed to 550 MWh, including two batteries in Ireland - the page does not split the megawatt-hours, Energy Storage the same day prints 240, 150 and 160, and 240 plus 150 plus 160 is 550
On 12 November 2026 Gore Street said its EU fund completed a second close and has committed €147m across 550 MWh, including two assets in the Republic of Ireland acquired in August 2026 and one in Poland signed in September 2026. The page prints a further 255 MWh and does not split the 550. It does not name the sites, print megawatts, or print the euros raised at the close. Energy Storage the same day prints Kilmannock at 120 MW / 240 MWh and Mucklagh at 75 MW / 150 MWh, and a Polish project at 40 MW / 160 MWh. Adding those three energy figures is 550 MWh, our arithmetic. 240 plus 150 is 390 MWh in Ireland. 390 divided by 550 is 0.709091 to six decimal places, our arithmetic. The company page does not print that share.
A buyer in Ireland can open two counters in the same month. One is a grant for panels on a roof. This page is a fund buying grid batteries. The euros on the fund page are not that grant.
Gore Street's page is marked Press Release 12 Nov 26. It says GS EU Fund completed a second close. The first close was in December 2025. A final close is targeted for the first half of 2027. The page says the fund has committed €147m across a portfolio of 550 MWh of storage. The portfolio includes two assets in the Republic of Ireland, acquired in August 2026, and one in Poland, signed in September 2026. The page does not name the three assets. It does not print megawatts. It does not say how many of the 550 MWh sit in Ireland.
The same page says the fund is progressing a further 255 MWh of advanced-stage opportunities, with more acquisitions expected before year-end. Adding 550 and 255 is 805 MWh, our arithmetic. The page does not print 805. A line on the page says the capital is already at work in Ireland and Poland, and that the fund is advancing further opportunities in Spain and Romania. The page does not print megawatt-hours for Spain or Romania. It does not put those countries inside the 255 MWh.
Cornerstone investors on the page are the European Investment Fund, and the National Treasury Management Agency as controller and manager of the Ireland Strategic Investment Fund. At the second close the fund welcomed a commitment from the Kingdom of Spain through the C&I Instrument under the National Recovery and Resilience Plan, plus further support from private capital. The page does not spell out C&I. It does not print Spain's euros. It does not print the euros raised at the second close. €147m is the commitment across the portfolio. The page does not print it as the size of the close.
Energy Storage, dated 12 November 2026, prints the site sizes the company page leaves blank. Kilmannock is 120 MW / 240 MWh. Mucklagh is 75 MW / 150 MWh. Both were acquired in August. Kilmannock is expected in the first quarter of 2028. Mucklagh is expected in the second quarter of 2028. The Polish project is 40 MW / 160 MWh, signed in September. Adding 240, 150 and 160 is 550 MWh, our arithmetic. Adding 240 and 150 is 390 MWh in Ireland. 390 divided by 550 is 0.709091 to six decimal places, our arithmetic. Adding 120 and 75 is 195 MW in Ireland. Adding 195 and 40 is 235 MW. 240 divided by 120 is 2. 150 divided by 75 is 2. 160 divided by 40 is 4. Those hours are our arithmetic. The company page does not print them. Energy Storage says the Polish project, on a line it attributes to Norton Rose Fulbright, holds a 17-year capacity market contract starting in 2030, with operations expected in the first quarter of 2028. The company page does not print that contract.
Energy Storage prints USD 163 million beside €147 million and does not print an exchange rate. 163 divided by 147 is 1.108844 to six decimal places, our arithmetic. 147 divided by 550 is 0.267273 to six decimal places, in millions of euro per megawatt-hour, our arithmetic. Neither page calls that figure a price. Energy Storage says the amount raised at the second close was not disclosed, and that a 24 September announcement expected an October close of about €210 million against a €500 million fund target. The 12 November company page does not print €210 million or €500 million. This note did not open the September page.
No workplace meter is named. The batteries are grid assets in a fund. A roof grant sits on a different counter. This page does not print the business solar grant, a 45% line, or €325,200. It does not print a kilowatt on a factory, a shop, a farm or a school. It does not print a cent the fund pays for a megawatt-hour.
Analogy: 550 MWh is one tank with three boxes and no label for which box holds which water. The company page prints the tank and the euros committed to it. It does not print how much of the water is in Ireland. €147m is the fund's commitment. It is not a sticker on a workplace roof.
Good: A 12 November company page with €147m and 550 MWh kept as a portfolio commitment, two Irish assets left unnamed on that page, and the site split kept on Energy Storage the same day, where 240 plus 150 plus 160 is 550.
Bad: No euros raised at the second close. No Spain amount. No megawatts on the company page. No share of the 550 MWh for Ireland on that page. The 2-hour and 4-hour lines are our division. The 17-year Polish contract is Energy Storage's account of an adviser. The €210 million and €500 million lines are Energy Storage's account of a September page this note did not open.
Ugly: Pasting €147m onto a roof grant. Treating 550 MWh as the Irish total. Treating 0.267273 million euro per megawatt-hour as a signed price. Treating 805 MWh as a figure the company page prints. Putting the Polish contract on an Irish site.
Soft next step: write €147m as a fund commitment across 550 MWh, leave Ireland's share off the company page, and leave the business solar grant on its own page.
Source: Gore Street Capital, 12 Nov 2026, GS EU second close. Primary for the 12 November 2026 release, a second close after a first close in December 2025, a final close targeted for the first half of 2027, €147m committed across 550 MWh, two assets in the Republic of Ireland acquired in August 2026, one asset in Poland signed in September 2026, a further 255 MWh, the European Investment Fund and the Ireland Strategic Investment Fund as cornerstone investors, and a Kingdom of Spain commitment through the C&I Instrument with no euro amount. The page does not name the sites, print megawatts, split the 550 MWh, or print the euros raised at the close. Adding 550 and 255 is 805, our arithmetic. Energy Storage, 12 Nov 2026, 550 MWh portfolio. Primary for Kilmannock at 120 MW / 240 MWh, Mucklagh at 75 MW / 150 MWh, commercial operation expected in the first and second quarters of 2028, a Polish project at 40 MW / 160 MWh, USD 163 million printed beside €147 million with no exchange rate, an undisclosed second-close raise, and a line that a 24 September announcement expected about €210 million against a €500 million target. The page attributes a 17-year Polish capacity contract, starting in 2030, to Norton Rose Fulbright. Adding 240, 150 and 160 is 550. 390 divided by 550 is 0.709091 to six decimal places, and 147 divided by 550 is 0.267273 to six decimal places, our arithmetic. The company page does not print that share or that rate.